La Rambla construction moves into Phase 2

Since June 16, the works have entered a new stage, with construction underway on the Raval side. This phase is expected to last 10 months.

The recovery of La Rambla as the city’s central hub is a priority during this mandate, in order to boost economic and commercial promotion and diversification and promote cultural activities that reconnect it with the city's residents and encourage them to use it as a space for strolling and socialising. The new layout will also improve accessibility and connections between the neighbourhoods of El Raval and El Gòtic.

Below is important information about the Rambla remodelling process, a comprehensive urban planning project with physical, social, cultural and economic dimensions.

Render
Render

DID YOU KNOW...?

  • Obres 2027

    Is the year the works will be completed

  • Cost 55,6 M.€

    Is the estimated cost of the new Rambla

  • Persones +70

    Is the number of social and cultural agents involved

THE PROJECT

Barcelona's boulevard

The work will be carried out longitudinally along the entire stretch of La Rambla, reducing the duration of the project in comparison to the time needed were it divided into sections.

Access to homes, shops, and car parks will be fully guaranteed, and loading and unloading will be restricted to the areas designated for this purpose. As a result, there will be disruptions to the bus lines that currently run along La Rambla, and when the time comes, appropriate information about alternative routes and transport options will be provided.

There will also be an impact in public transportOpen in a new window and on the waste collection service, both for residents and commercial businesses.

A drilling machine working on the ground of la Rambla in Barcelona. Beside it, the foot of a lamppost characteristic of this area, while in the background a crowd watches intently at the beginning of the works.

Community

The boulevard of the people

The Rambla project has made progress thanks to the work of the Rambla Community which operates through two committees: the Cultural Organisations committee and the Cultural Institutions committee.

Their work has led to the implementation of the “Rambla cultural line” which has culturally re-energised the different Àgores. A total of 100 activities have been scheduled through the involvement of about seventy of these social and cultural agents seeking to enrich their projects and opened them to the general public. 

View of the stands and people on la Rambla

The Espai Rambla

Information point.

Espai Rambla is the place to go to get information on and find out about the project to transform Barcelona’s La Rambla, one of the most unique and well-known boulevards in the world.

  • Address: Palau de La Virreina (La Rambla, 99).
  • Opening times: from Monday to Friday, 10:15 am to 6:15 pm.
  • Opening times during August: from Monday to Friday, 10:15 am to 2:15 pm.

Work maps

Here, you’ll find maps of the sections where work is in progress, planned mobility and loading/unloading spaces. 

These maps will change as work progresses.